Client: Asanko Gold Mines
Project: PW Facilities
Duration: November 2014 – January 2015
Responsibilities:
- Coordinating with General Manager in preparing Civil/Structural and Architectural drawings such as Accommodation Units, Office Blocks, High Cube Container building, Security Huts for client's approval using AutoCAD.
Client: Subsea 7 (Tullow Oil Ghana Ltd)
Project: TEN – Fabrication Yard
Duration: 2014 – January 2015
Responsibilities:
- Coordinating with General/Project Manager in preparing Civil/Structural drawings such as cross sections through ground improvement, drainage and electrical pit/trench details, machine rolling pit layouts, and sections for client's approval using AutoCAD.
Client: Ghana Airport Company Ltd
Project: GACL Car Park near Airport Shell
Duration: 2014 – January 2015
Responsibilities:
- Preparing topographical drawings from data surveyed by Site Engineers using AutoCAD Civil 3D.
- Drafting layout for parking space and detailed drawings for Civil/Structural and electrical works with the coordination of Project and M & E Managers for client's approval using AutoCAD.
Client: Ghana Airport Company Ltd
Project: Kotoka International Airport (KIA) Southern Apron
Duration: 2010 - January 2015
Responsibilities:
- Preparing topographical drawings from data surveyed by Site Engineers using AutoCAD Civil 3D.
- Coordinating with Project Manager to review invert and cover levels for drainage layout using AutoCAD.
- Preparing detail drawings for manholes/catch pits, sections and profile for existing and proposed surfaces for consultant's approval using AutoCAD.
- Performing monthly earthworks/stockpile analysis using survey data from Site Engineers to include in the monthly report AutoCAD Civil 3D.
- Preparing a rebar schedule for Project Manager's approval to use by steel benders using AutoCAD.
- Assisting Site Engineers in setting out by extracting coordinates from CAD files AutoCAD Civil 3D.
- Assisting Quantity Surveyor in extracting linear and superficial measurement used for their checks using AutoCAD.
- Preparing As-built drawing for Civil works and Airfield Ground Lighting Duct and Pit Systems using AutoCAD.
Client: Ghana Airport Company Ltd
Project: KIA Phase 3 Rehabilitation
Duration: November 2014 – 2015
Responsibilities:
- Preparing topographical drawings from data surveyed by Site Engineers using AutoCAD Civil 3D.
- Performing monthly stockpile analysis using survey data from Site Engineers to include in the monthly report using AutoCAD Civil 3D.
- Prepare milling and regulating surface exhibits for engineering decision using AutoCAD Civil 3D.
- Assisting Site Engineers in setting out for centerline and edge lights, pavement markings, AGL pit positions by extracting coordinates using AutoCAD Civil 3D.
- Assisting Quantity Surveyor in extracting linear (such as duct lengths) and areas for tonnage of asphalt required for daily production checks using AutoCAD.
- Preparing As-built drawing for Civil works and Airfield Ground Lighting Duct and Pit Systems using AutoCAD Civil 3D.
Client: FMC Technologies
Project: New High Bay Workshop at Takoradi Port
Duration: 2010 - 2014
Responsibilities:
- Coordinating with General Manager to prepare site layout, drainage crossover slab layout, cover slab, test pit location sketch, the location of test pit lights, wash bay layout and slab joint details using AutoCAD.
- Preparing general arrangement layout for foundations, floor slabs, and bund wall structural details for warehouse extension 1 & 2 using AutoCAD.
Client: Ghana Airport Company Ltd
Project: KIA Airfield Fire & Rescue Station
Duration: 2010 -2011
Responsibilities:
- Reviewing of washroom layout, door and window schedule and provide details using AutoCAD.
- Preparing ceiling layout for the station using AutoCAD.
- Realigning door and windows using AutoCAD.
- Providing civil/structural details for external works using AutoCAD.
- Coordinating with M & E Manager to review electrical, mechanical and plumbing drawings using AutoCAD.
- Prepare As-built drawings for the works using AutoCAD.
Client: FMC Technologies
Project: Shipping Container Facilities
Duration: 2010
Responsibilities:
- Designing architectural layouts, plan view, elevation and section drawings and prepare electrical layout and details for 20ft and 40ft container facilities such as offices and canteen with General/Project and M & E Managers for client's approval using AutoCAD.
Client: Tullow Oil Ghana Ltd
Project: Chemical Storage and Decant Facility
Duration: 2011
Responsibilities:
- Coordinating with General/ M & E Managers to review offshore tank and Decant Facility layout drawing received using AutoCAD.
- Preparing manhole and drainage layout, plinth and bund wall layout and, a section for transfer diaphragm pump, slab, and joint details, ramp details, layout and sections, drainage and fence post details, and electrical works, diesel tank, compressor, and gen set using AutoCAD.
Client: Tullow Oil Ghana Ltd
Project: New Aviation Check In Facility at KIA
Duration: 2012
Responsibilities:
- Preparing layout drawing for demolition and proposed building and electrical works fusing AutoCAD.
Client: LADOL Integrated Logistics Free Zone Enterprise
Project: LADOL Hard Standing Area – Phase 1, Takoradi
Duration: 2012-2013
Responsibilities:
- Coordinating with Project Manager to prepare layouts, details for harbour walls, slabs (including joints) and drains for client's approval.
- Preparing slab schedule for tracking placed concrete areas to aid Quantity Surveyors' in preparing their monthly report.