Using of communicators and process meter for calibration and stroking of electrical devices such as; Pressure Indicator Transmitters(PIT), Temperature Indicator Transmitters(TIT), Level Indicator Transmitters(LIT), Flow Indicator Transmitters(FIT), Pressure switches(PS), Flow control valves(FCV), Level control valves(LCV), Limit switches(LS), Shutdown valves(SDV), Blowdown valves(BDV), Positioners and Solenoid valves(SoV). Termination and troubleshooting in RIO cabinets such as ESD, F&G, SIS and PCS.
Conducting of cause and effect for installations.
Maintenance done for the following equipments;
1. HVAC units.
2. Generators.
3. Water treatment plants.
4. Smart Home systems.
Installation, termination and commissioning of the following equipments;
1. Mini-substations 11KV
2. Ring main units.
3. RI/O cabinets.
4. Variable frequency drives (VFD).
5. Pump system.
6. Electrical Motors(STAR and DELTA).
Preparation and commissioning of the following activities ;
1. Promoted safety and work site awareness by identifying and removing potential hazards and effectively training team members in safety protocols.
2. Supervised job site operations to ensure consistent safety and a hazard-free work area.
3. Organized and maintained all material, labor, and equipment before, during, and after each job task.
4. Supervised in the installation of electrical and instrumentation panels.
5. Directed work and inspected task performed.
6. Fabricated and installed cable trays and cable tray support.
7. Prepared electrical cable to terminate.
8. Installation and termination of Generators.
9. Installation and termination of Transformers
10. Installation and termination of Electrical switchgears.
Installation and commissioning of the following activities;
1. Supervised in the installation of electrical and instrumentation panels such as SIS, PCS, F&G and ESD cabinets.
2. Supervised in the installation of Gas detectors and other electrical
devices such as Temperature IndicatorTransmitters(TIT), Level Indicator Transmitters(LIT), Flow Indicator Transmitters(FIT), Pressure Indicator Transmitters(PIT), Gas detectors, Flame detectors(Transmitters and receivers).
3. Supervised in cable pulling from panels to field.
4. abrications and installation of cable trays and accessories.
5. Installation of fire alarm system.
Conducted the following activities;
1.Supervised job site operations to ensure consistent safety and a hazard-free working area.
2. Supervised the installation of lighting fixtures in and around the tank farm and the pump raft.
3. Termination of electrical motors.
4. Termination of transformer cables at both transformer and MCC.
5. Termination of generator cables.
6. Glanding and termination of pump cables in the pump raft.
7. Cable tray fabrication and installation.
Construction and commissioning of the following activities;
1. Pulled Anode-flexible cable for Cathodic Protection System.
2. Spliced Anode-flexible cable at the end of every circuit by using the splicing kit.
3. Prepared coated pipes for termite or CAD weld for Cathodic Protection System.
4. Installed Test Point Station (TPS) and terminated cables for Cathodic Protection System.
5. Installed current Transformer or Rectifier for Cathodic Protection System and terminate cables.
6. nstalled Spark Gap between pipes.
7. Assisted the Vendor to commission all Cathodic Protection System on site.
8. Promoted safety and work site awareness by identifying and removing potential hazards and effectively training team members in safety protocols.
Conducted the following activities;
1. Supervised job site operations to ensure consistent safety and a hazardfree work area.
2. Directed work and inspected task performed.
3. Read and interpreted schematics and wiring diagrams for lighting, fire alarm system, telecommunications, and other electrical systems to team members to perform tasks.
4. Organized and maintained all material, labor, and equipment before, during, and after each job task.
5. Installed electrical instrumentation devices.
6. Installed lighting fixtures.
7. Pulling of Cable, Glanding and Termination.
8. Conduit pipe fabrication and installation.
Conducted the following activities;
1. Installed, tested and serviced alarm systems, ensuring that they functioned correctly.
2. Installed electrical instruments, gland and terminated.
3. Routed electrical cables.
4. Fabricated and installed cable trays and cable tray support.
Conducted and commissioned the following activities;
1. Tested energized and de-energized circuits, following test procedures and assisted in specialized test procedures.
2. ead schematics and electrical wiring diagram for lighting system.
3. Assembled street light poles.
4. Installed and repaired equipment based on mechanical drawings and electrical prints.
5. Installed and coupled electrical panel.
6. Prepared electrical cable to terminate.
7. Repaired electrical equipment using hand and power tools and testing and diagnostic equipment.
The following activities were conducted;
1. Performed general maintenance on electrical and electronic systems.
2. Installed new units and replaced part of existing machines according to specification and established safety guidelines such as Limit switches, solenoids, valves, sensors, etc.
3. Analyses drawings for the purpose of identifying location of new and existing electrical systems and determining the efficient installation of additional systems.
4. Prepared a preventive maintenance schedule for all machines and made sure every little fault is eliminated to avoid breakdown.
The following activities were conducted;
1. Maintenance on Low Voltage Lines.
2. Sub-station maintenance.
3. Construction of new overhead Lines.
4. Laying and troubleshooting of underground cables.